OCR Text |
Show 49-39) The Texas Company - Construction of Office Building - Casper, Wyoming a) Their Contract No. NY-MW-454 b) Dated - July 26, 1949 c) Performance Bond; $143,650 - by Aetna Casualty & Surety Payment Bond: 71,825 d) Premium Paid - $1,436.50 e) Compensation and Liability Insurance - Employers Mutual f) Completion Date; No specific dates set. To commence at once and complete as soon as possible. g) Total Amount - Orig. Contract $143,650.00 Addition 250.00 143,900.00 Deduction 371.00 Final Estimate: $143,529.00 h) In Charge of Salt Lake District 49-40 Standard Oil Company of California - Addition to 100-Octane Plant Richmond Refinery_________ a) Compensation and Liability Insurance - Employers Mutual b) Completion Date - October 10, 1949 c) Total Amount -$15,500 d) In Charge of Richmond Office 49-41 General Chemical Company - 2/18/49 - P.O. No. 654 - Resurface concrete under existing tanks, Richmond Req. No. 225 - Remove & replace disintegrated concrete - Richmond, California a) b) Dated - Feb. 18, 1949 c) Compensation and Liability Insurance - Employers Mutual 49-42 Eaton and Smith - Contractors - two contracts - San Francisco, California a) Dated - August 3, 1949 - No. 3989 - Install 4" steel pipe sections, etc. Oleum Refinery -$600.00 Dated - August 11, 1964 - No. 2551 - Paint steel lines with hot asphalt - Oleum Refinery - $65.00 b) Compensation & Liability Insurance - Employers Mutual Liability Insurance Co. c) In charge of Richmond Office |