Show Track Prefabrication Workshop The tracklaying consisted principally of putting in place the 24-meter track panels which had been prefabricated in the workshop. The prefabrication workshop comprised - in the order of operations: - 4 welding benches which enabled the alignment of the ends of two 12-meter rails so that the weld could be performed. The 24-meter rails were moved out on conveyors and, after cooling, they were ground and marked, before being stockpiled. - The assembly shop for these track panels comprised six benches, served by traveling cranes. The prefabricated panels were loaded on lorries which could swivel and slide. - Each unit of three lorries carried a load of six track panels. The loads were joined together by couplings which were attached to the rails of the bottom panels. A train of 7 loads, maximum, was dispatched each day to the tracklaying site. Utah's share of the total revenue of this target estimate bonus contract was $11, 991, 315. The breakdown of the joint venture participation was: CITRA. 35%, Utah 35% and Taylor Woodrow 30%. 13) Mt. Lyell Stripping The work involved the removal of approximately 1,150,000 cubic yards of rock overburden over-laying the ore body in the open cut. Modern equipment, including self-propelled drills, heavy duty shovels and 27-ton capacity rear dump trucks, expedited removal of rock in benches approxi- mately 50 ft. high. This project was located near Queenstown, Tasmania, and the owner was the Mt. Lyell Mining and Railway Co. The schedule of rates contract was dated November 1959 and the work was completed in June of 1962. The cost of the project was $1, 538,555. 14) Campbell's Soup Plant The construction and design of a food processing and soft drink bottling plant for Campbell's Soups (Aust.) Pty. Ltd. in Shepparton, Victoria, Australia. The work commenced in November of i960 and the main plant was completed on schedule, February, 1962. Office areas and the laboratory were completed 3 months prior. Preparation of complete specifications by Utah included: Factory: Approximately 140,000 sq. ft. in area. Amenities Block & Cafeteria for 350 employees . |